Do it
J-1046
Declan McCloskey, Claudy · Solar + Battery. The details, photos, paperwork, stock and cost of the job, on one page.
Stage 8 of 11 · Install
The crew fits it, ticks the steps and adds photos. What they use comes off the van and onto the job’s cost.
1Enquiry
2Survey
3Quote
4Sold
5Network application
6Order the kit
7Load the van
8Install
9Sign off
10Invoice and payment
11The numbers
Customer and system
CustomerDeclan McCloskey
WhereClaudy, BT47 4AB
System18 × 400W panels (7.2kWp), Hybrid 5.0kW inverter, 15.6kWh battery
RoofSouth + West, 35°, Slate
NIE NetworksG99/NI · Approved · NIE-G99-5210
CrewSean G
Install18 Nov
SalespersonRonan Kelly
QuoteQ-2245
Photos 1
Roof, beforeDual-aspect slate
Paperwork
NIE Networks: G99/NI approval
NIE Networks · 11 NovDone
NIE Networks · 11 NovDone
EIC
On commissioningLater
On commissioningLater
Scheme certificate
LaterLater
LaterLater
Notes
Two-string dual-aspect. Install 18 Nov with Sean G and Conor F.