HSHS RenewablesDo it / J-1042
Sample data. Not connected to your Xero.
Do it

J-1042

Aidan Kelly, Strabane · Solar + Battery. The details, photos, paperwork, stock and cost of the job, on one page.

1Enquiry
2Survey
3Quote
4Sold
5Network application
6Order the kit
7Load the van
8Install
9Sign off
10Invoice and payment
11The numbers

Customer and system

CustomerAidan Kelly
WhereStrabane, BT82 8DP
System16 × 400W panels (6.4kWp), Hybrid 5.0kW inverter, 10.4kWh battery
RoofSouth-west, 35°, Slate
NIE NetworksG99/NI · Approved · NIE-G99-4471
CrewLiam B, Sean G
Install16 Nov
SalespersonNiamh McLaughlin
QuoteQ-2231

Photos 4

Roof, beforeSW slate roof, 35° pitch, clear of shading
Array layout16 panels, 2 columns, 1 string
Inverter + batteryUtility cupboard, 2× 5.2kWh stacked
Consumer unitHenley block + generation meter fitted

Paperwork

NIE Networks: G99/NI approval
NIE Networks · 25 Oct
Done
EIC (BS 7671)
Due on commissioning
Due
Commissioning (BS EN 62446)
Due tomorrow
Due
Scheme certificate
After commissioning
Later
Handover pack
On handover
Later

Notes

Customer wants app monitoring set up on handover. Battery bay pre-cleared.

Stock set aside

5 of 6 loaded
CodeLineQtyFrom
PNL-400400W all-black panel16Van Sean GLoaded
INV-HYB-5.0Hybrid inverter 5.0kW1WarehouseLoaded
BAT-5.2Battery module 5.2kWh2WarehouseLoaded
MNT-RAILMounting rail (2.1m)12Van Liam BLoaded
OPT-DCDC optimiser16Van Sean GLoaded
CAB-DC-6DC cable 6mm²40Van Liam BTo load

Cost and margin

38.7% margin
Equipment (panels, inverter, battery)£4,820
Consumables + mounting£640
Labour (2 installers × 2 days)£980
Scaffolding (sub-contract)£450
Cost£6,890
Sold for£11,240
The job made£4,350