Mary Gallagher, Coleraine · Solar PV. The details, photos, paperwork, stock and cost of the job, on one page.
Stage 9 of 11 · Sign off
Tests and certificates, the handover pack to the customer, registration.
1Enquiry
2Survey
3Quote
4Sold
5Network application
6Order the kit
7Load the van
8Install
9Sign off
10Invoice and payment
11The numbers
Customer and system
CustomerMary Gallagher
WhereColeraine, BT52 1RU
System10 × 400W panels (4kWp), Hybrid 3.6kW inverter
RoofSouth, 30°, Concrete
NIE NetworksG98/NI · Notified · NIE-G98-3391
CrewLiam B
Install6 Nov
SalespersonAoife O’Kane
Photos 3
Roof, beforeSouth concrete-tile roof
Array10 all-black panels
Handover packSigned and emailed
Paperwork
NIE Networks: G98/NI notification
NIE Networks · 7 OctDone
NIE Networks · 7 OctDone
EIC (BS 7671)
Liam B · 8 NovDone
Liam B · 8 NovDone
Commissioning (BS EN 62446)
Passed · 8 NovDone
Passed · 8 NovDone
Scheme certificate
Issued · 10 NovDone
Issued · 10 NovDone
Handover pack
Sent · 10 NovDone
Sent · 10 NovDone